Silver Group
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Silver City A And B BuildingP52100011509 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Silver City Mhada And Mhada 1P52100020985 | Pimpri Chinchawad (M Corp.) | 2019 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Silver City C And DP52100026575 | Haveli | 2020 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Silver City A And B Building (P52100011509).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology