Silver Group

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Silver City A And B BuildingP52100011509Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Dec 201930 Dec 2021+24 months
Silver City Mhada And Mhada 1P52100020985Pimpri Chinchawad (M Corp.)2019Certificate Signed30 Dec 202130 Dec 2021On date
Silver City C And DP52100026575Haveli2020Certificate Signed30 Jun 202630 Oct 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silver City A And B Building+24 mo
  • Silver City Mhada And Mhada 1On date
  • Silver City C And D+4 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Silver City A And B Building (P52100011509).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.