Silicon Lifespaces Llp
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as Issued to Silicon Lifespaces LLP
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Silicon PrideP51800056474 | Chembur | 2024 | Certificate Signed | 30 Nov 2027 | 30 Nov 2027 | On date |
| Silicon AvenuePM1180002400006 | Kurla | 2024 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Silicon Avenue (PM1180002400006).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology