Sidhivinayak Constructions

Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date40%2 of 5 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
OpulenceP51800002068Kurla2017Not reported31 Dec 201830 Dec 2020+24 months
ApurvaP51800003149Kurla2017Not reported31 Dec 201830 Dec 2020+24 months
Shivpuri Building No.10 Chs Ltd - Shivam HeightsP51800008516Kurla2017Not reported31 Dec 201830 Dec 2020+24 months
Sidhivinayak FloraP51800033003Kurla2022Not reported31 Dec 2026—On date
Roop ApartmentsP51800046002Kurla2022Not reported31 Mar 2025—On date
Kranti HeightsP51800076833Kurla2024Not reported30 Sep 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Opulence+24 mo
  • Apurva+24 mo
  • Shivpuri Building No.10 Chs Ltd - Shivam Heights+24 mo
  • Sidhivinayak FloraOn date
  • Roop ApartmentsOn date
  • Kranti HeightsOn date

Track record notes

  • 2 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Opulence (P51800002068).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology