Siddhivinayak Properties

Company or firm · 4 projects · 4 MahaRERA registrations · 1 reported completed

4Projects4 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bhalchandra ApartmentP50500014197Nagpur (M Corp.)2017Completed31 Mar 2019—On date
Ekdant EnclaveP50500014264Nagpur (M Corp.)2017Certificate Signed31 Mar 201931 Mar 2019On date
Ganraj-IV ResidencyP50500020230Nagpur (M Corp.)2019Certificate Signed30 Dec 202130 Dec 2021On date
Ganraj HeightsP50500032200Nagpur (M Corp.)2021Certificate Signed31 Dec 202331 Dec 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bhalchandra ApartmentOn date
  • Ekdant EnclaveOn date
  • Ganraj-IV ResidencyOn date
  • Ganraj HeightsOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology