Siddhi Gaurav Enterprises

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Highland Park Building 2- K25 Wing A Phase 2P51700005485Thane (M Corp.)2017Certificate Signed31 Dec 202630 Apr 2027+4 months
Highland Park Building 6 And 7- K23 Phase 1P51700006811Thane (M Corp.)2017Certificate Signed31 Dec 201931 Dec 2019On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Highland Park Building 2- K25 Wing A Phase 2+4 mo
  • Highland Park Building 6 And 7- K23 Phase 1On date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Highland Park Building 2- K25 Wing A Phase 2 (P51700005485).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology