Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Siddheshwar Anant ResidencyP52800047225Khed (M Cl)2022Certificate Signed31 May 202531 May 2025On date
Raaya ResidencyP52800049709Veral2023Certificate Signed31 May 202531 May 2025On date
Siddheshwar VihaanP52800055518Khed (M Cl)2024Certificate Signed31 May 202630 Sep 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Siddheshwar Anant ResidencyOn date
  • Raaya ResidencyOn date
  • Siddheshwar Vihaan+4 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Siddheshwar Vihaan (P52800055518).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology