Siddhesh Developers
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| ShagunP52100026627 | Pune (M Corp.) | 2020 | Certificate Signed | 31 Mar 2021 | 30 Mar 2022 | +12 months |
| Siddhesh ShreeramP52100047903 | Karve Nagar | 2022 | Certificate Signed | 31 Aug 2025 | 31 Aug 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Shagun (P52100026627).
Regulatory cases across projects
- DeregisteredDeregistered: Siddhesh Shreeram · Siddhesh Shreeram · P52100047903
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology