Siddharth Properties
Company or firm · 7 projects · 9 MahaRERA registrations
Projects79 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date13%1 of 8 past their proposed date, not extended
Median delay+33 movs RERA proposed date · 7 extended
Regulatory cases3MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Success SquareP52100001813 | Pune (M Corp.) | 2017 | Not reported | 31 Jul 2019 | 30 Jan 2021 | +18 months |
| Saarrthi SwadeshP52100003849 | Jambhul | 2017 | Not reported | 30 Sep 2018 | 19 Jul 2024 | +70 months |
| Saarrthi SkybayP52100004803 | Mahalunge | 2017 | Not reported | 31 May 2019 | 30 Nov 2020 | +18 months |
| Saarrthi Savvy Homes IIP52100016105 | Hinjavadi (Ct) | 2018 | Not reported | 30 Dec 2022 | 31 Mar 2026 | +39 months |
| West SquareP52100016161 | Pune (M Corp.) | 2018 | Not reported | 31 Mar 2019 | — | On date |
| Saarrthi SkybayP52100016176 | Mahalunge | 2018 | Not reported | 30 Dec 2022 | 30 Sep 2025 | +33 months |
| Saarrthi SkybayP52100022081 | Mahalunge | 2019 | Not reported | 30 Mar 2024 | 31 Dec 2026 | +33 months |
| Saarrthi SupremusP52100027384 | Mulshi | 2020 | Not reported | 30 Sep 2022 | 31 Dec 2027 | +63 months |
| Saarrthi SkybizzP52100054933 | Mahalunge | 2024 | Not reported | 31 Mar 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 8 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 70 months, for Saarrthi Swadesh (P52100003849).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: SAARRTHI SKYBAY II (Regulatory Case No. 344 OF 2025) dated 04 April, 2025. · Saarrthi Skybay · P52100016176 · 4 Apr 2025
- Regulatory orderRegulatory order: PROJECT NAME:SAARRTHI SAVVY HOMES II (Regulatory Case No.163 OF 2024) dated 24 April 2024. · Saarrthi Swadesh · P52100003849 · 24 Apr 2024 · the order may refer to a related project
- Regulatory orderRegulatory order: PROJECT NAME:SAARRTHI SAVVY HOMES II (Regulatory Case No.163 OF 2024) dated 24 April 2024. · West Square · P52100016161 · 24 Apr 2024 · the order may refer to a related project
- Regulatory orderRegulatory order: PROJECT NAME:SAARRTHI SAVVY HOMES II (Regulatory Case No.163 OF 2024) dated 24 April 2024. · Saarrthi Savvy Homes II · P52100016105 · 24 Apr 2024
- Regulatory orderRegulatory order: PROJECT NAME: SAARRTHI SKYBAY II (Regulatory Case No.134 of 2024) dated 1 February 2024. · Saarrthi Skybay · P52100016176 · 1 Feb 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology