Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shyam OrnateP51600029306 | Nashik (M Corp.) | 2021 | Certificate Signed | 27 Aug 2023 | 27 Aug 2023 | On date |
| Shyam VistaP51600052139 | Nashik (M Corp.) | 2023 | Certificate Signed | 30 May 2025 | 30 May 2025 | On date |
| Shyam AristoP51600052249 | Nashik (M Corp.) | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Shyam Aristo (P51600052249).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology