Skip to content

Shudhanshu Infrastructures Pvt Ltd

Company or firm · 4 projects · 4 MahaRERA registrations

Also appears as SUDHANSHU INFRASTRUCTURES PVT LTD

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+28 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sudhanshu ImperiaP51800003303Kurla2017Certificate Signed1 Feb 202030 Dec 2021+22 months
Vishnu Bhaskar Chs LtdP51800015748Kurla2018Certificate Signed10 Sep 201926 Mar 2024+54 months
Sudhanshu Imperia Wing CP51800027547Kurla2020Certificate Signed30 Jun 202331 Mar 2026+33 months
Bhandup Amol Chs LtdP51800050455Bhandup2023Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sudhanshu Imperia+22 mo
  • Vishnu Bhaskar Chs Ltd+54 mo
  • Sudhanshu Imperia Wing C+33 mo
  • Bhandup Amol Chs Ltd+4 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Vishnu Bhaskar Chs Ltd (P51800015748).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology