Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Spring ValleyP52100002725Haveli2017Not reported31 Dec 2019—On date
Spring Valley Phase IIP52100013807Charholi2017Not reported30 Jun 202130 Dec 2022+18 months
Spring ValleyP52100033571Haveli2022Not reported31 Dec 2029—On date
Spring Valley Phase IVP52100047250Wadmukhwadi2022Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Spring ValleyOn date
  • Spring Valley Phase II+18 mo
  • Spring ValleyOn date
  • Spring Valley Phase IVOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Spring Valley Phase II (P52100013807).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology