Shruti Buildtech LLP
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Radhe AnantamPR1260002502659 | Wadmukhwadi | 2026 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Radhe Anantam Wing A and BPM1260002602463 | Wadmukhwadi | 2026 | Not reported | 31 Dec 2031 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Radhe Anantam (PR1260002502659).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology