Shrushti Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shrushti Aarambh, Wing - C of Phase - IP51700015554Badlapur (M Cl)2018Not reported30 Dec 2022—On date
Shrushti PrarambhP51700016101Badlapur (M Cl)2018Not reported30 Dec 2022—On date
Shrushti Aarambh - Wing A1, B and B1 of Phase - IIIP51700027627Badlapur (M Cl)2020Not reported30 Oct 202329 Oct 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shrushti Aarambh, Wing - C of Phase - IOn date
  • Shrushti PrarambhOn date
  • Shrushti Aarambh - Wing A1, B and B1 of Phase - III+12 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shrushti Aarambh - Wing A1, B and B1 of Phase - III (P51700027627).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology