Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anand HomesP51700005026Kalyandombivali (M Corp.)2017Not reported30 Dec 2020—On date
Anand Homes Wing CP51700019124Kalyan2019Not reported30 May 2022—On date
Anand Homes Wing DP51700024095Kalyandombivali (M Corp.)2020Not reported30 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anand HomesOn date
  • Anand Homes Wing COn date
  • Anand Homes Wing DOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology