Skip to content
Deedo home
Menu

Shrikrishna Ramchandra Marathe

Individual promoter · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+10 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SAANJ CO OP HSG SOC PraposedP52000019822Dahiwali T. Waredi2019Not reported30 Jun 202230 Jun 2024+24 months
Saayam VisavaP51700024133Dombivli2020Not reported30 May 202331 Mar 2024+10 months
Ekopa Co Op Housing SocietyP51700053969Dombivli2023Not reported30 Apr 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • SAANJ CO OP HSG SOC Praposed+24 mo
  • Saayam Visava+10 mo
  • Ekopa Co Op Housing SocietyOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for SAANJ CO OP HSG SOC Praposed (P52000019822).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology