Skip to content
Deedo home
Menu

Shrijee Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Silver BirchP52100023407Talegaon Dabhade (M Cl)2019Certificate Signed30 Dec 202230 Dec 2022On date
Silver HeightsP52100029598Talegaon Dabhade (M Cl)2021Certificate Signed31 Dec 202431 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silver BirchOn date
  • Silver HeightsOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology