Shri Sati Builders And Developers Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anand Bhavan - PristinoP51800008855Kurla2017Not reported31 Mar 201830 Sep 2018+6 months
Mannat TowerP51800009212Kurla2017Not reported31 Mar 201831 Mar 2019+12 months
Girivan ShivkunjP51800011754Kurla2017Not reported31 Mar 202030 Mar 2022+24 months
Girivan VarenyaaPR1180002601861Ghatkopar2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anand Bhavan - Pristino+6 mo
  • Mannat Tower+12 mo
  • Girivan Shivkunj+24 mo
  • Girivan VarenyaaOn date

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Girivan Shivkunj (P51800011754).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology