Shri R N Goli Developers

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kalpita HeightsP52600004884Solapur (M Corp.)2017Not reported1 Dec 201830 Dec 2022+48 months
R N Goli CelebrationP52600005031Solapur (M Corp.)2017Not reported1 Nov 2018—On date
Ramchandra EmpireP52600005386Solapur (M Corp.)2017Not reported31 Dec 2019—On date
Kushi ResidencyP52600007050Solapur (M Corp.)2017Not reported31 Jul 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kalpita Heights+48 mo
  • R N Goli CelebrationOn date
  • Ramchandra EmpireOn date
  • Kushi ResidencyOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Kalpita Heights (P52600004884).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology