Shri Nakoda Enterprises

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ratan Luxuria Ratan AnnexP51900002984Ward Abcd2017Not reported31 Dec 2018—On date
Ratan AddressP51900032985Ward Gnorth2022Not reported30 Sep 2026—On date
Ratan ElitePR1170002501443Mumbai City2025Not reported31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ratan Luxuria Ratan AnnexOn date
  • Ratan AddressOn date
  • Ratan EliteOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology