Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Shri Labsons Builders And Developers Private Limited

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+17 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Samarth KrupaP52100010272Pimpri Chinchawad (M Corp.)2017Certificate Signed15 Dec 201815 Oct 2021+34 months
Shri Labsons ApartmentP52100054707Moshi2024Certificate Signed20 Dec 202620 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Samarth Krupa+34 mo
  • Shri Labsons ApartmentOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 34 months, for Shree Samarth Krupa (P52100010272).
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology