Shri Labsons Builders And Developers Pvt Ltd
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as Shri Labsons Builders And Developers Private Limited
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+17 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shree Samarth KrupaP52100010272 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 15 Dec 2018 | 15 Oct 2021 | +34 months |
| Shri Labsons ApartmentP52100054707 | Moshi | 2024 | Certificate Signed | 20 Dec 2026 | 20 Dec 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 34 months, for Shree Samarth Krupa (P52100010272).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: Shri Labsons Apartment · Shri Labsons Apartment · P52100054707
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology