Shri Gajanan Builder & Developers

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Gajanan Vihar IIP50500028542Pipla2021Certificate Signed30 Mar 202430 Mar 2024On date
Shree Gajanan Vihar IIIP50500052255Pipla2023Completed30 Jun 2026—On date
Shree Gajanan Vihar IVP50500054697Pipla2024Certificate Signed31 Mar 202631 Jul 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Gajanan Vihar IIOn date
  • Shree Gajanan Vihar IIIOn date
  • Shree Gajanan Vihar IV+4 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Shree Gajanan Vihar IV (P50500054697).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology