Shri Balaji Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mayuresh ResidencyP52700025312Phaltan (M Cl)2020Certificate Signed30 Dec 202530 Dec 2025On date
Mayuresh HeightsP52700047223Phaltan (M Cl)2022Certificate Signed31 Mar 202731 Mar 2027On date
Mayuresh ParkP52700079780Kolki (Ct)2025Certificate Signed31 Dec 203030 Apr 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mayuresh ResidencyOn date
  • Mayuresh HeightsOn date
  • Mayuresh Park+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Mayuresh Park (P52700079780).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology