Shrey Infra
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sky CrystaP52000016593 | Bokadvira | 2018 | Not reported | 31 Jan 2021 | — | On date |
| Sky CreevaP52000016618 | Bokadvira | 2018 | Not reported | 31 Jan 2021 | 31 Jul 2022 | +18 months |
| Sky CrownP52000016727 | Bokadvira | 2018 | Not reported | 31 Jan 2021 | — | On date |
| Sky TwinkleP52000032362 | Uran | 2021 | Not reported | 31 Dec 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Sky Creeva (P52000016618).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology