Shreenathji Organisers Pvt. Ltd
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as SHREENATHJI ORGANISERS PVT LTD · SHREENATHJI ORGANISERS PVT. LTD.
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mayuresh DeltaP52000010297 | Ulawe | 2017 | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Delta HeightsP52000030771 | Ulawe | 2021 | Certificate Signed | 31 Jul 2026 | 31 Jul 2026 | On date |
| Delta LuxuriaP51700035130 | Navi Mumbai (M Corp.) | 2022 | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 months |
| Delta IconP51700047643 | Navi Mumbai (M Corp.) | 2022 | Certificate Signed | 31 Jul 2027 | 30 Nov 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Delta Luxuria (P51700035130).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology