Shreenath Enterprises
Company or firm · 5 projects · 6 MahaRERA registrations
5Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Parasnath Garden- Sno 200-1-2P99000011584 | Umroli | 2017 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
| Parasnath TownshipP99000015590 | Panchali | 2018 | Certificate Signed | 31 Mar 2020 | 31 Mar 2028 | +96 months |
| Parasnath CornerP99000018754 | Umroli | 2018 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| Parasnath NagariP99000026724 | Umroli | 2020 | Certificate Signed | 30 Sep 2027 | 30 Sep 2027 | On date |
| Parasnath NagariP99000027533 | Umroli | 2020 | Certificate Signed | 30 Jun 2023 | 31 Dec 2027 | +54 months |
| Parasnath TownshipP99000055881 | Panchali | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 96 months, for Parasnath Township (P99000015590).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology