Shreeji Landmarks LLP
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shreeji Infinia PlusPM1220002500198 | Nashik | 2025 | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 months |
| Gangajal By ShreejiPR1220002500256 | Aanandwali | 2025 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Shreeji InsperiaPM1220002500272 | Wadala Shivar | 2025 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Shreeji IconicPM1220002501612 | Nashik | 2025 | Certificate Signed | 30 Jun 2031 | 30 Oct 2031 | +4 months |
| Shreeji AuspiciaPM1220002600732 | Nashik | 2026 | Certificate Signed | 30 Jun 2032 | 30 Oct 2032 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Shreeji Infinia Plus (PM1220002500198).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology