Skip to content
Deedo home
Menu

Shreeji Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
GreenvilleP52100024364Somatane2020Certificate Signed31 Dec 202630 Apr 2027+4 months
Arianna HomesP52100053619Somatane2023Certificate Signed31 Mar 202731 Jul 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Greenville+4 mo
  • Arianna Homes+4 mo

Track record notes

  • Longest extension on record: 4 months, for Greenville (P52100024364).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology