Shreeji Associates
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Green ParkP52000013578 | Mahad | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Green Park Phase -IIP52000017468 | Chambharkhind | 2018 | Certificate Signed | 30 Dec 2024 | 30 Dec 2025 | +12 months |
| Green Park H WingP52000080977 | Chambharkhind | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Green Park Phase -II (P52000017468).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology