Shree Venkatesh Realties

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Venkatesh Lake Life Phase 1P52100001126Ambegaon Kh2017Certificate Signed30 Jun 201830 Jun 2018On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Venkatesh Lake Life Phase 1On date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology