Shree Vedant Krupa
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shree Umiya Darshan Co Operative Housing Society LtdP51700033487 | Badlapur (M Cl) | 2022 | Not reported | 30 Nov 2024 | — | On date |
| Vedant MatoshreeP51700046258 | Badlapur (M Cl) | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Sharmila SadanPR1330002502539 | Kulgaon | 2026 | Not reported | 31 Mar 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
