Shree Sonigara Realcon
Company or firm · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Signature Park G And H BuildingP52100019960 | Thergaon | 2019 | Not reported | 1 Apr 2024 | — | On date |
| Signature Park C And D BuildingP52100020943 | Thergaon | 2019 | Not reported | 1 Apr 2024 | — | On date |
| Signature Park E F I And J BuildingsP52100027402 | Thergaon | 2020 | Not reported | 30 Jun 2026 | — | On date |
| Signature Park Building M MhadaP52100032493 | Thergaon | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Signature RitzP52100052042 | Thergaon | 2023 | Not reported | 31 Dec 2028 | — | On date |
| Signature Park K L N BuildingsPR1260002502756 | Thergaon | 2026 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology