Shree Shivbali Builders Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 5 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Akshay EnclaveP99000030582 | Vasaivirar City (M Corp) | 2021 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Shree Township Phase 2P99000035083 | Kambalgaon | 2022 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Shree Township Phase 2P99000051250 | Kambalgaon | 2023 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Shree Township Phase 2P99000053270 | Kambalgaon | 2023 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Shree ChintamaniPM1180002601360 | Gorai | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Akshay Enclave (P99000030582).
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: SHREE TOWNSHIP PHASE 2 · Shree Township Phase 2 · P99000051250
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology