Skip to content

Shree Shivam Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+20 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tulsa ParkP51700005797Khadegolavali2017Certificate Signed30 Jun 202130 Jun 2024+36 months
Silver PlazaPR1330002600303Khadegolavali2026Certificate Signed31 Mar 202931 Jul 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tulsa Park+36 mo
  • Silver Plaza+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Tulsa Park (P51700005797).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology