Shree Shakti Developers

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 4 past their proposed date, not extended
+33 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kaveri KrishnaP51700005237Thane2017Not reported31 Dec 201730 Sep 2018+9 months
KoelP51700007920Thane2017Certificate Signed30 Dec 202131 Dec 2025+48 months
KoynaP51700009082Thane2017Not reported30 Jun 202129 Dec 2022+18 months
KabiniP51700010423Thane2017Not reported30 Dec 202131 Dec 2025+48 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kaveri Krishna+9 mo
  • Koel+48 mo
  • Koyna+18 mo
  • Kabini+48 mo

Track record notes

  • 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Koel (P51700007920).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology