Shree Shakti Developers
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 4 past their proposed date, not extended
+33 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kaveri KrishnaP51700005237 | Thane | 2017 | Not reported | 31 Dec 2017 | 30 Sep 2018 | +9 months |
| KoelP51700007920 | Thane | 2017 | Certificate Signed | 30 Dec 2021 | 31 Dec 2025 | +48 months |
| KoynaP51700009082 | Thane | 2017 | Not reported | 30 Jun 2021 | 29 Dec 2022 | +18 months |
| KabiniP51700010423 | Thane | 2017 | Not reported | 30 Dec 2021 | 31 Dec 2025 | +48 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 48 months, for Koel (P51700007920).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology