Skip to content
Deedo home
Menu

Shree Samarth Residency

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Samarth DarshanP52000001859Dhamote2017Not reported31 Dec 2018—On date
Shree Siddhi Vinayak SamarthP52000017396Dhamote2018Not reported30 Dec 2021—On date
Shree Samarth ParadiseP52000049281Neral2023Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Samarth DarshanOn date
  • Shree Siddhi Vinayak SamarthOn date
  • Shree Samarth ParadiseOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology