Shree Saibaba Grihanirmiti Private Limited

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashar MetroP51700007507Vartaknagar2017Certificate Signed30 Dec 202430 Dec 2024On date
Ashar MetroP51700009352Vartaknagar2017Certificate Signed30 Dec 202430 Dec 2024On date
Aasara Co-Op. Housing Society Ltd.P51700012205Vartaknagar2017Certificate Signed31 Dec 201930 Dec 2021+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashar MetroOn date
  • Ashar MetroOn date
  • Aasara Co-Op. Housing Society Ltd.+24 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Aasara Co-Op. Housing Society Ltd. (P51700012205).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology