Shree Sai Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Capetown VillasP51600002951Igatpuri (M Cl)2017Lapsed30 Jul 202030 Mar 2022+20 months
Seasons HarmonyP51700034223Gandhare2022Certificate Signed31 Mar 202531 Mar 2025On date
Sai Gokul ViharP51700079127Kalyandombivali (M Corp.)2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Capetown Villas+20 mo
  • Seasons HarmonyOn date
  • Sai Gokul Vihar+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 20 months, for Capetown Villas (P51600002951).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology