Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shubh Laxmi Appartment Bld A Phase 1P52000027605Nagothane2020Certificate Signed30 Sep 202427 Sep 2025+12 months
Shubh Laxmi Apartment Bld B Phase IIP52000051178Roha2023Certificate Signed31 Mar 202631 Jul 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shubh Laxmi Appartment Bld A Phase 1+12 mo
  • Shubh Laxmi Apartment Bld B Phase II+4 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shubh Laxmi Appartment Bld A Phase 1 (P52000027605).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology