Shree Rajendra Developers
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shubh Laxmi Appartment Bld A Phase 1P52000027605 | Nagothane | 2020 | Certificate Signed | 30 Sep 2024 | 27 Sep 2025 | +12 months |
| Shubh Laxmi Apartment Bld B Phase IIP52000051178 | Roha | 2023 | Certificate Signed | 31 Mar 2026 | 31 Jul 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Shubh Laxmi Appartment Bld A Phase 1 (P52000027605).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology