Shree Naman Developers Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as SHREE NAMAN DEVELOPERS PRIVATE LIMITED

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+54 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Naman HabitatP51800004108Andheri2017Not reported30 Jun 202231 Dec 2026+54 months
Naman PremierP51800008002Andheri2017Not reported31 Mar 202031 Dec 2025+69 months
Naman Fifty EightPM1180002600360Ambivali2026Not reported31 Mar 2031—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Naman Habitat+54 mo
  • Naman Premier+69 mo
  • Naman Fifty EightOn date

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 69 months, for Naman Premier (P51800008002).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology