Shree Mahalakshmi Constructions

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Sumitra ApartmentsP51800011651Borivali2017Certificate Signed31 Dec 201831 Dec 2018On date
Shree Mahalakshmi ResidencyP51900045601Mumbai City2022Certificate Signed30 Jun 202630 Oct 2026+4 months
Shree Mahalakshmi KunjP51800078455Vileparle2024Certificate Signed31 Dec 202630 Apr 2027+4 months
Shree Mahalakshmi SaburiP51800079394Kolekalyan2025Certificate Signed31 May 202730 Sep 2027+4 months
Shree Mahalakshmi TrinityP51900079405Ward Gnorth2025Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Sumitra ApartmentsOn date
  • Shree Mahalakshmi Residency+4 mo
  • Shree Mahalakshmi Kunj+4 mo
  • Shree Mahalakshmi Saburi+4 mo
  • Shree Mahalakshmi Trinity+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Shree Mahalakshmi Residency (P51900045601).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology