Shree Mahalakshmi Constructions
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shree Sumitra ApartmentsP51800011651 | Borivali | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Shree Mahalakshmi ResidencyP51900045601 | Mumbai City | 2022 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
| Shree Mahalakshmi KunjP51800078455 | Vileparle | 2024 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Shree Mahalakshmi SaburiP51800079394 | Kolekalyan | 2025 | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 months |
| Shree Mahalakshmi TrinityP51900079405 | Ward Gnorth | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Shree Mahalakshmi Residency (P51900045601).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology