Company or firm · 5 projects · 6 MahaRERA registrations

Projects56 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%6 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vraj BungalowP51600009649Nashik2017Not reported30 Dec 2023—On date
Vraj BungalowP51600009871Nashik2017Not reported30 Dec 2023—On date
Vraj CapitalP51600010869Nashik2017Not reported30 Jun 2023—On date
Vraj VillaP51600025502Satpur2020Not reported30 Jun 2023—On date
Vraj DhamP51600025518Nashik2020Not reported30 Jun 2025—On date
Vraj Life SpaceP51600026362Nashik (M Corp.)2020Not reported30 Jun 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vraj BungalowOn date
  • Vraj BungalowOn date
  • Vraj CapitalOn date
  • Vraj VillaOn date
  • Vraj DhamOn date
  • Vraj Life SpaceOn date

Track record notes

  • 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology