Shree Gurukrupa Builders And Developers

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Niwas ApartmentP50900028795Brahmapuri (M Cl)2021Not reported30 Jun 2023—On date
Shree Saikrupa LayoutP50900054942Khedmakta2024Not reported31 Dec 2025—On date
Shree Gurukrupa LayoutP50900055195Khedmakta2024Not reported31 Dec 2025—On date
Shree Royal HeightsP50900079417Brahmapuri (M Cl)2025Not reported30 Jun 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Niwas ApartmentOn date
  • Shree Saikrupa LayoutOn date
  • Shree Gurukrupa LayoutOn date
  • Shree Royal HeightsOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology