Shree Buildcon Realty

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Gajanan EstateP51600001483Chehedi Bk2017Not reported31 Dec 2019—On date
Shree Sai VillasP51600011733Sinnar2017Not reported31 Mar 201930 Sep 2020+18 months
Shree Shubhankar NiwasP51600032500Chehedi Bk2022Not reported31 Dec 202431 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Gajanan EstateOn date
  • Shree Sai Villas+18 mo
  • Shree Shubhankar Niwas+12 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Shree Sai Villas (P51600011733).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology