Shree Amrut Sai Developer Pvt.Ltd
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Amrut Sai Plaza Ph 2P51500011307 | Aurangabad (M Corp.) | 2017 | Certificate Signed | 31 Jul 2026 | 31 Jul 2026 | On date |
| Golden HeightsP51500055184 | Aurangabad (M Corp.) | 2024 | Certificate Signed | 31 Aug 2030 | 31 Dec 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Golden Heights (P51500055184).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: AMRUT SAI PLAZA PH 2 (Regulatory Case No.80 of 2023) dated 22 November 2023. · Amrut Sai Plaza Ph 2 · P51500011307 · 25 Nov 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology