Shivesh Realty Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shivesh SapphireP52000052187Wahal2023Certificate Signed30 Oct 202630 Oct 2026On date
Shivesh EmeraldP51700052476Navi Mumbai (M Corp.)2023Certificate Signed31 Jul 202630 Nov 2026+4 months
Shivesh AurumP52000053493Kharghar2023Certificate Signed31 Dec 202631 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivesh SapphireOn date
  • Shivesh Emerald+4 mo
  • Shivesh AurumOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Shivesh Emerald (P51700052476).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology