Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shivam GreencourtP52100010035 | Mahalunge | 2017 | Not reported | 30 Oct 2021 | — | On date |
| Ghanwat SquareP52100025403 | Mahalunge | 2020 | Not reported | 30 Jun 2023 | 30 Nov 2025 | +29 months |
| Ghanwat IconP52100080877 | Kharabwadi (Ct) | 2025 | Not reported | 31 Dec 2027 | — | On date |
| Gurukrupa HeightsPM1261012601158 | Mahalunge | 2026 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 29 months, for Ghanwat Square (P52100025403).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 4 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology