Shivaji Narayan Thorat
Individual promoter · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date25%1 of 4 past their proposed date, not extended
Median delay+33 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tejaswi HarmonyP52000019981 | Pargaon | 2019 | Not reported | 25 Apr 2021 | 25 Oct 2025 | +54 months |
| Tejaswi Royal 1P52000023011 | Ulawe | 2019 | Not reported | 30 Mar 2023 | 31 Dec 2025 | +33 months |
| Tejaswi Royal 2P52000023071 | Ulawe | 2019 | Not reported | 30 Mar 2023 | 31 Dec 2025 | +33 months |
| Tejaswini EmeraldP52000023556 | Ulawe | 2019 | Not reported | 30 Mar 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 54 months, for Tejaswi Harmony (P52000019981).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology