Shiva Rameehans Constructions LLP

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv AashrayPM1180002600079Chakala2026Certificate Signed30 Jan 202830 May 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv Aashray+4 mo

Track record notes

  • Longest extension on record: 4 months, for Shiv Aashray (PM1180002600079).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology