Skip to content
Deedo home
Menu

Shiv Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hariom TwinsP51600028657Nashik (M Corp.)2021Not reported30 Sep 2024—On date
Hariom Avenue ApartmentP51600047681Nashik (M Corp.)2022Not reported31 Mar 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hariom TwinsOn date
  • Hariom Avenue ApartmentOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology