Shiv Corporation

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv SamarthP51700016324Badlapur (M Cl)2018Certificate Signed30 Sep 202030 Sep 2020On date
Shiv ParadiseP51700046607Badlapur (M Cl)2022Certificate Signed31 Dec 202531 Dec 2025On date
Shiv ParadiseP51700055322Badlapur (M Cl)2024Certificate Signed31 Dec 202630 Apr 2027+4 months
Shiv ElysiumPR1330002502526Shirgaon2026Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv SamarthOn date
  • Shiv ParadiseOn date
  • Shiv Paradise+4 mo
  • Shiv Elysium+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Shiv Paradise (P51700055322).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology